(a) Neither a recipient nor any participant in the development process, including public or private nonprofit or for-profit entities, or any of their contractors, may commit HUD assistance under a program listed in § 58.1(b) on an activity or project until HUD or the state has approved the recipient's RROF and the related certification from the responsible entity. In addition, until the RROF and the related certification have been approved, neither a recipient nor any participant in the development process may commit non-HUD funds on or undertake an activity or project under a program listed in § 58.1(b) if the activity or project would have an adverse environmental impact or limit the choice of reasonable alternatives.
(b) If a project or activity is exempt under § 58.34, or is categorically excluded (except in extraordinary circumstances) under § 58.35(b), no RROF is required and the recipient may undertake the activity immediately after the responsible entity has documented its determination as required in § 58.34(b) and § 58.35(d), but the recipient must comply with applicable requirements under § 58.6.
(c) If a recipient is considering an application from a prospective subrecipient or beneficiary and is aware that the prospective subrecipient or beneficiary is about to take an action within the jurisdiction of the recipient that is prohibited by paragraph (a) of this section, then the recipient will take appropriate action to ensure that the objectives and procedures of NEPA are achieved.
(d) An option agreement on a proposed site or property is allowable prior to the completion of the environmental review if the option agreement is subject to a determination by the recipient on the desirability of the property for the project as a result of the completion of the environmental review in accordance with this part and the cost of the option is a nominal portion of the purchase price. There is no constraint on the purchase of an option by third parties that have not been selected for HUD funding, have no responsibility for the environmental review and have no say in the approval or disapproval of the project.
(e)
(f)