[Federal Register Volume 63, Number 126 (Wednesday, July 1, 1998)]
[Notices]
[Pages 35921-35924]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-17430]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. ER98-1850-000, et al.]


California Independent System Operator Corporation, et al.; 
Electric Rate and Corporate Regulation Filings

June 22, 1998.
    Take notice that the following filings have been made with the 
Commission:

1. California Independent System Operator Corporation

[Docket No. ER98-1850-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between 
Automated Power Exchange, Inc., and the ISO for acceptance by the 
Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

2. California Independent System Operator Corporation

[Docket No. ER98-1851-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between 
Enron Power Marketing, Inc., and the ISO for acceptance by the 
Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

3. California Independent System Operator Corporation

[Docket No. ER98-1854-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between LG&E 
Energy Marketing, Inc., and the ISO for acceptance by the Commission. 
The ISO states that Amendment No. 1, modifies the Agreement, as 
directed by the Commission, to comply with the Commission's order 
issued December 17, 1997 in Pacific Gas and Electric Co., 81 FERC para. 
61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

4. California Independent System Operator Corporation

[Docket No. ER98-1856-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between Duke 
Energy Trading & Marketing, L.L.C. and the ISO for acceptance by the 
Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

5. California Independent System Operator Corporation

[Docket No. ER98-1857-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator

[[Page 35922]]

Corporation (ISO), tendered for filing Amendment No. 1, to the Meter 
Service Agreement for Scheduling Coordinators between Salt River 
Project Agriculture Improvement and Power District and the ISO for 
acceptance by the Commission. The ISO states that Amendment No. 1, 
modifies the Agreement, as directed by the Commission, to comply with 
the Commission's order issued December 17, 1997 in Pacific Gas and 
Electric Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

6. California Independent System Operator Corporation

[Docket No. ER98-1858-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between PG&E 
Energy Services Corporation and the ISO for acceptance by the 
Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

7. California Independent System Operator Corporation

[Docket No. ER98-1859-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between 
Vitol Gas & Electric, L.L.C. and the ISO for acceptance by the 
Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

8. California Independent System Operator Corporation

[Docket No. ER98-1862-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between 
Arizona Public Service Company and the ISO for acceptance by the 
Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

9. California Independent System Operator Corporation

[Docket No. ER98-1863-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between 
Power Resource Managers, L.L.C., and the ISO for acceptance by the 
Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

10. California Independent System Operator Corporation

[Docket No. ER98-1866-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between 
Edison Source and the ISO for acceptance by the Commission. The ISO 
states that Amendment No. 1, modifies the Agreement, as directed by the 
Commission, to comply with the Commission's order issued December 17, 
1997 in Pacific Gas and Electric Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

11. California Independent System Operator Corporation

[Docket No. ER98-1867-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between 
PacifiCorp and the ISO for acceptance by the Commission. The ISO states 
that Amendment No. 1, modifies the Agreement, as directed by the 
Commission, to comply with the Commission's order issued December 17, 
1997 in Pacific Gas and Electric Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

12. California Independent System Operator Corporation

[Docket No. ER98-1889-000]

    Take notice that on June 17, 1998, the California Independent 
System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
to the Meter Service Agreement for Scheduling Coordinators between the 
City of Seattle, City Light Department and the ISO for acceptance by 
the Commission. The ISO states that Amendment No. 1, modifies the 
Agreement, as directed by the Commission, to comply with the 
Commission's order issued December 17, 1997 in Pacific Gas and Electric 
Co., 81 FERC para. 61,320 (1997).
    The ISO states that this filing has been served on all parties 
listed on the official service list in the above-referenced docket.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

13. Rochester Gas and Electric Corporation

[Docket Nos. ER98-2510-000 and ER98-2621-000]

    Take notice that on June 17, 1998, Rochester Gas and Electric 
Corporation (RG&E), filed a response to a deficiency letter received 
from the Director, Division of Rate Applications, dated

[[Page 35923]]

May 18, 1998 (May 18, Letter) in these proceedings. As part of this 
response, RG&E submits two Service Agreements for service to Energetix, 
Inc., and NEV East LLC. RG&E states that these Service Agreements 
address all the items raised in the May 18, Letter.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

14. Carolina Power & Light Company

[Docket No. ER98-3385-000]

    Take notice that on June 17, 1998, Carolina Power & Light Company 
(CP&L), tendered for filing un-executed Service Agreements between CP&L 
and 108 eligible buyers.1
---------------------------------------------------------------------------

    \1\ The list of the 108 eligible buyers can be found in 
Attachment A of the application filed June 17, 1998 in the above-
docketed proceeding.
---------------------------------------------------------------------------

    Service to each eligible buyer will be in accordance with the terms 
and conditions of CP&L's Market-Based Rates Tariff, FERC Electric 
Tariff No. 4, for sales of capacity and energy at market-based rates.
    Copies of the filing were served upon the North Carolina Utilities 
Commission and the South Carolina Public Service Commission.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

15. Puget Sound Energy, Inc.

[Docket No. ER98-3392-000]

    Take notice that on June 17, 1998, Puget Sound Energy, Inc., as 
Transmission Provider, tendered for filing a Service Agreement for Firm 
Point-To-Point Transmission Service (Firm Point-To-Point Service 
Agreement) and a Service Agreement for Non-Firm Point-To-Point 
Transmission Service (Non-Firm Point-To-Point Service Agreement) with 
Avista Energy, Inc. (Avista), as Transmission Customer.
    A copy of the filing was served upon Avista.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

16. Fortistar Power Marketing LLC

[Docket No. ER98-3393-000]

    Take notice that on June 17, 1998, Fortistar Power Marketing LLC 
(FPM), tendered for filing pursuant to Rule 205, 18 CFR 385.205, a 
petition for waivers and blanket approvals under various regulations of 
the Commission and for an order accepting its FERC Electric Rate 
Schedule No. 1, to be effective sixty days from the date of this 
filing. In transactions where FPM will sell electric energy at 
wholesale, it proposes to make such sales on rates, terms and 
conditions to be mutually agreed to with the purchasing party.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

17. Carolina Power & Light Company

[Docket No. ER98-3394-000]

    Take notice that on June 17, 1998, Carolina Power & Light Company 
(CP&L), tendered for filing executed Service Agreements between CP&L 
and the following eligible buyers: Allegheny Power Service Corporation; 
The Energy Authority; The Power Company of America; and Northern 
Indiana Public Service Company. Service to each eligible buyer will be 
in accordance with the terms and conditions of CP&L's Market-Based 
Rates Tariff, FERC Electric Tariff No. 4, for sales of capacity and 
energy at market-based rates.
    Copies of the filing were served upon the North Carolina Utilities 
Commission and the South Carolina Public Service Commission.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

18. Carolina Power & Light Company

[Docket No. ER98-3395-000]

    Take notice that on June 17, 1998, Carolina Power & Light Company 
(CP&L), tendered for filing un-executed Service Agreements between CP&L 
and the following eligible buyers: Avista Energy, Inc.; Cargill-
Alliant, LLC; First Energy Trading and Power Marketing Incorporated; 
Plum Street Energy Marketing; and QST Energy Trading. Service to each 
eligible buyer will be in accordance with the terms and conditions of 
CP&L's Market-Based Rates Tariff, FERC Electric Tariff No. 4, for sales 
of capacity and energy at market-based rates.
    Copies of the filing were served upon the North Carolina Utilities 
Commission and the South Carolina Public Service Commission.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

19. Arizona Public Service Company

[Docket No. ER98-3396-000]

    Take notice that on June 17, 1998, Arizona Public Service Company 
(APS), tendered for filing a Service Agreement under APS' FERC Electric 
Tariff, Original Volume No. 3, for service to the California 
Independent System Operator Corporation.
    A copy of this filing has been served on the Arizona Corporation 
Commission and the California Independent System Operator Corporation.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

20. New York State Electric & Gas Corporation

[Docket No. ER98-3397-000]

    Take notice that on June 17, 1998, New York State Electric & Gas 
Corporation (NYSEG), tendered for filing pursuant to Section 205 of the 
Federal Power Act and Section 35.13 of the Federal Energy Regulatory 
Commission's (FERC or Commission) Regulations, a request for 
modification of its tax factor applicable to service rendered under 
Schedules 7 and 8 and Attachment H of NYSEG's OATT.
    NYSEG requests an effective date of August 17, 1998, for the new 
tax factor.
    NYSEG has served copies of the filing on the parties on the 
official service list of the OATT. In addition, NYSEG has mailed copies 
of the filing to NYPSC, NYPA, and the customers taking service under 
the OATT.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

21. Southern Company Services, Inc.

[Docket No. ER98-3398-000]

    Take notice that on June 17, 1998, Southern Company Services, Inc. 
(SCSI), acting on behalf of Alabama Power Company, Georgia Power 
Company, Gulf Power Company, Mississippi Power Company and Savannah 
Electric and Power Company (collectively referred to as Southern 
Companies), filed a service agreement under Southern Companies' Market-
Based Rate Power Sales Tariff (FERC Electric Tariff, Original Volume 
No. 4) with The XERXE Group, Inc. SCSI states that the service 
agreements will enable Southern Companies to engage in short-term 
market-based rate sales to this customer.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

22. Western Resources, Inc.

[Docket No. ER98-3401-000]

    Take notice that on June 17, 1998, Western Resources, Inc., 
tendered for filing an agreement between Western Resources and Ameren 
Services Company, Western Resources and Missouri Public Service, 
Western Resources and Koch Energy Trading, Inc., Western Resources and 
PacifiCorp Power Marketing, Inc., and Western Resources and Omaha 
Public Power District. Western Resources states that the purpose of the 
agreements is to permit the customers to take service

[[Page 35924]]

under Western Resources' market-based power sales tariff on file with 
the Commission. The agreements are proposed to become effective May 19, 
1998, May 18, 1998, May 20, 1998, May 28, 1998 and June 17, 1998, 
respectively.
    Copies of the filing were served upon Ameren Services Company, 
Missouri Public Service, Koch Energy Trading, Inc., PacifiCorp Power 
Marketing, Inc., Omaha Public Power District, and the Kansas 
Corporation Commission.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

23. PJM Interconnection, L.L.C.

[Docket No. ER98-3402-000]

    Take notice that on June 17, 1998, PJM Interconnection, L.L.C. 
(PJM), tendered for filing amendments to the service agreements for 
Network Integration Transmission Service for Delmarva Power & Light 
Company and PP&L, Inc., so as to reflect that, commencing June 1, 1998, 
the load of the Easton Utilities Commission will be served by PP&L 
rather than Delmarva.
    Copies of this filing were served upon Delmarva, PP&L, Easton, the 
Maryland Public Service Commission, and the Pennsylvania Public Utility 
Commission.
    PJM requests an effective date of June 1, 1998, for the amendments 
to the service agreements.
    Comment date: July 7, 1998, in accordance with Standard Paragraph E 
at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of these filings are on file with 
the Commission and are available for public inspection.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-17430 Filed 6-30-98; 8:45 am]