[Federal Register Volume 64, Number 65 (Tuesday, April 6, 1999)]
[Notices]
[Page 16727]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-8375]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP99-275-000]


Great Lakes Gas Transmission Limited Partnership; Notice of 
Request Under Blanket Authorization

March 31, 1999.
    Take notice that on March 29, 1999, Great Lakes Gas Transmission 
Limited Partnership (Great Lakes), One Woodward Avenue, Suite 1600, 
Detroit, Michigan 48226, filed a request, pursuant to Sections 157.205 
and 157.212 of the Regulations, 18 CFR 157.205 and 157.212, of the 
Commission's regulations for authorization under Great Lakes' blanket 
certificate issued in Docket No. CP90-2053-000 to construct and operate 
a new meter station, to be located in Marenisco Township, Gogebic 
County, Michigan, all as more fully set forth in the application which 
is on file with the Commission and open to public inspection.\1\ This 
filing may be viewed on the web at: http://www.ferc.fed.us/online/
rims.htm (call 202-208-2222 for assistance).
---------------------------------------------------------------------------

    \1\ Great Lakes states that a copy of its Request is available 
for inspection electronically on its website at http://
www.greatlakesgas.com/transport/ferc/marenisco.htm.
---------------------------------------------------------------------------

    The proposed facilities, it is said, would be located entirely 
within Great Lakes' existing right-of-way and would be used to deliver 
up to 1,560 dekatherms per day of natural gas to Northern States Power 
Company--Wisconsin (NSP-WI). Great Lakes states that NSP-WI would 
utilize these volumes to provide new natural gas service in the 
Township of Marenisco, which Township has not heretofore received 
natural gas service. Great Lakes further states that the estimated cost 
of constructing the new facilities is $291,000; the actual cost of 
construction would be borne by NSP-WI through payment of a contribution 
in aid of construction. Great Lakes further states that natural gas 
would be transported to the proposed meter station pursuant to an 
existing firm transportation agreement between itself and NSP-WI.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file a motion to 
intervene or notice of intervention, pursuant to Rule 214 of the 
Commission's Procedural Rules, 18 CFR 385.214, and pursuant to Section 
157.205 of the Commission's Regulations, 18 CFR 157.205, a protest to 
the Request. If no protest is filed within the time allowed therefor, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 99-8375 Filed 4-5-99; 8:45 am]