NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-254 and 50-265]


Exelon Generation Company, LLC; Notice of Consideration of 
Issuance of Amendment to Facility Operating License, Proposed No 
Significant Hazards Consideration Determination, and Opportunity for a 
Hearing

    The U.S. Nuclear Regulatory Commission (the Commission) is

[[Page 62836]]

considering issuance of an amendment to Facility Operating License Nos. 
DPR-29 and DPR-30 issued to Exelon Generation Company, LLC (Exelon, the 
licensee), for operation of the Quad Cities Nuclear Power Station, 
Units 1 and 2, located in Rock Island County, IL.
    The proposed amendment would revise the Updated Safety Analysis 
Report (UFSAR) to allow lifting heavier loads with the reactor building 
crane during the Unit 1 refueling outage beginning in November 2002.
    Before issuance of the proposed license amendment, the Commission 
will have made findings required by the Atomic Energy Act of 1954, as 
amended (the Act), and the Commission's regulations.
    The Commission has made a proposed determination that the amendment 
request involves no significant hazards consideration. Under the 
Commission's regulations in Title 10 of the Code of Federal Regulations 
(10 CFR), Sec.  50.92, this means that operation of the facility in 
accordance with the proposed amendment would not (1) involve a 
significant increase in the probability or consequences of an accident 
previously evaluated; or (2) create the possibility of a new or 
different kind of accident from any accident previously evaluated; or 
(3) involve a significant reduction in a margin of safety. As required 
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue 
of no significant hazards consideration, which is presented below:

    1. The proposed changes do not involve a significant increase in 
the probability or consequences of an accident previously evaluated.
    The proposed changes will allow use of the reactor building 
crane at Quad Cities Nuclear Power Station (QCNPS) during power 
operations to lift heavy loads up to 125 tons for removal and re-
installation activities for the reactor cavity shield blocks during 
the Unit 1 refueling outage (i.e., Q1R17). The reactor building 
crane has additional margin for a total lifted load of 125 tons with 
single failure-proof features if a Design Basis Earthquake (DBE) is 
not assumed. Exelon has qualitatively demonstrated that the 
probability of a DBE occurring during the limited duration 
(estimated to be 24 hours) of the request is very small. The 
probability of load drop accidents previously evaluated is not 
increased since the capacity of the reactor building crane equals or 
exceeds the weight of the reactor cavity shield blocks.
    Therefore, the proposed changes do not involve a significant 
increase in the probability or consequences of an accident 
previously evaluated.
    2. The proposed changes do not create the possibility of a new 
or different kind of accident from any accident previously 
evaluated.
    The proposed changes allow use of the QCNPS reactor building 
crane for a limited duration to lift heavy loads up to a total of 
125 tons during removal and re-installation activities for the 
reactor cavity shield blocks. The reactor building crane has 
additional margin for a lifted load of 125 tons with single failure-
proof features if a DBE is not assumed. The probability of a DBE 
during the limited duration of the request is very small. Therefore, 
the single failure-proof features ensure that the proposed changes 
provide an equivalent level of safety and will not create the 
possibility of a new or different kind of accident from any accident 
previously evaluated.
    3. The proposed changes do not involve a significant reduction 
in a margin of safety.
    The reactor building crane is rated for lifting loads up to 125 
tons. The NRC has approved qualification of the QCNPS reactor 
building crane as single failure-proof for loads of up to 110 tons. 
The proposed change allows use of the crane for a limited duration 
to lift loads up to 125 tons. Existing safety margins are enhanced 
when lifting loads up to 125 tons if a DBE is not assumed, and 
Exelon has demonstrated that the probability of a DBE during the 
limited duration of the request is very small. Therefore, it is 
concluded that the proposed changes do not result in a significant 
reduction in the margin of safety.

    The NRC staff has reviewed the licensee's analysis and, based on 
this review, it appears that the three standards of 10 CFR 50.92(c) are 
satisfied. Therefore, the NRC staff proposes to determine that the 
amendment request involves no significant hazards consideration.
    The Commission is seeking public comments on this proposed 
determination. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendment until the 
expiration of the 30-day notice period. However, should circumstances 
change during the notice period such that failure to act in a timely 
way would result, for example, in derating or shutdown of the facility, 
the Commission may issue the license amendment before the expiration of 
the 30-day notice period, provided that its final determination is that 
the amendment involves no significant hazards consideration. The final 
determination will consider all public and State comments received. 
Should the Commission take this action, it will publish in the Federal 
Register a notice of issuance and provide for opportunity for a hearing 
after issuance. The Commission expects that the need to take this 
action will occur very infrequently.
    Written comments may be submitted by mail to the Chief, Rules and 
Directives Branch, Division of Administrative Services, Office of 
Administration, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001, and should cite the publication date and page number of 
this Federal Register notice. Written comments may also be delivered to 
Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, 
Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Documents may 
be examined, and/or copied for a fee, at the NRC's Public Document 
Room, located at One White Flint North, 11555 Rockville Pike (first 
floor), Rockville, Maryland.
    The filing of requests for hearing and petitions for leave to 
intervene is discussed below.
    By November 7, 2002, the licensee may file a request for a hearing 
with respect to issuance of the amendment to the subject facility 
operating license and any person whose interest may be affected by this 
proceeding and who wishes to participate as a party in the proceeding 
must file a written request for a hearing and a petition for leave to 
intervene. Requests for a hearing and a petition for leave to intervene 
shall be filed in accordance with the Commission's ``Rules of Practice 
for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
persons should consult a current copy of 10 CFR 2.714,\1\ which is 
available at the Commission's Public Document Room, located at One 
White Flint North, 11555 Rockville Pike (first floor), Rockville, 
Maryland, or electronically on the Internet at the NRC Web site http://www.nrc.gov/reading-rm/doc-collections/cfr/. If there are problems in 
accessing the document, contact the Public Document Room Reference 
staff at 1-800-397-4209, 301-415-4737, or by e-mail to [email protected]. If 
a request for a hearing or petition for leave to intervene is filed by 
the above date, the Commission or an Atomic Safety and Licensing Board, 
designated by the Commission or by the Chairman of the Atomic Safety 
and Licensing Board Panel, will rule on the request and/or petition; 
and the Secretary or the designated Atomic Safety and Licensing Board 
will issue a notice of hearing or an appropriate order.
---------------------------------------------------------------------------

    \1\ The most recent version of Title 10 of the Code of Federal 
Regulations, published January 1, 2002, inadvertently omitted the 
last sentence of 10 CFR 2.714(d) and paragraphs (d)(1) and (d)(2) 
regarding petitions to intervene and contentions. For the complete, 
corrected text of 10 CFR 2.714(d), please see 67 FR 20884; April 29, 
2002.
---------------------------------------------------------------------------

    As required by 10 CFR 2.714, a petition for leave to intervene 
shall set forth with particularity the interest of

[[Page 62837]]

the petitioner in the proceeding, and how that interest may be affected 
by the results of the proceeding. The petition should specifically 
explain the reasons why intervention should be permitted with 
particular reference to the following factors: (1) The nature of the 
petitioner's right under the Act to be made party to the proceeding; 
(2) the nature and extent of the petitioner's property, financial, or 
other interest in the proceeding; and (3) the possible effect of any 
order which may be entered in the proceeding on the petitioner's 
interest. The petition should also identify the specific aspect(s) of 
the subject matter of the proceeding as to which petitioner wishes to 
intervene. Any person who has filed a petition for leave to intervene 
or who has been admitted as a party may amend the petition without 
requesting leave of the Board up to 15 days prior to the first 
prehearing conference scheduled in the proceeding, but such an amended 
petition must satisfy the specificity requirements described above.
    Not later than 15 days prior to the first prehearing conference 
scheduled in the proceeding, a petitioner shall file a supplement to 
the petition to intervene which must include a list of the contentions 
which are sought to be litigated in the matter. Each contention must 
consist of a specific statement of the issue of law or fact to be 
raised or controverted. In addition, the petitioner shall provide a 
brief explanation of the bases of the contention and a concise 
statement of the alleged facts or expert opinion which support the 
contention and on which the petitioner intends to rely in proving the 
contention at the hearing. The petitioner must also provide references 
to those specific sources and documents of which the petitioner is 
aware and on which the petitioner intends to rely to establish those 
facts or expert opinion. Petitioner must provide sufficient information 
to show that a genuine dispute exists with the applicant on a material 
issue of law or fact. Contentions shall be limited to matters within 
the scope of the amendment under consideration. The contention must be 
one which, if proven, would entitle the petitioner to relief. A 
petitioner who fails to file such a supplement which satisfies these 
requirements with respect to at least one contention will not be 
permitted to participate as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing, including the opportunity to present evidence and cross-
examine witnesses.
    If a hearing is requested, the Commission will make a final 
determination on the issue of no significant hazards consideration. The 
final determination will serve to decide when the hearing is held.
    If the final determination is that the amendment request involves 
no significant hazards consideration, the Commission may issue the 
amendment and make it immediately effective, notwithstanding the 
request for a hearing. Any hearing held would take place after issuance 
of the amendment.
    If the final determination is that the amendment request involves a 
significant hazards consideration, any hearing held would take place 
before the issuance of any amendment.
    A request for a hearing or a petition for leave to intervene must 
be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
Adjudications Staff, or may be delivered to the Commission's Public 
Document Room (PDR), located at One White Flint North, 11555 Rockville 
Pike (first floor), Rockville, Maryland, by the above date. Because of 
the continuing disruptions in delivery of mail to United States 
Government offices, it is requested that petitions for leave to 
intervene and requests for hearing be transmitted to the Secretary of 
the Commission either by means of facsimile transmission to 301-415-
1101 or by e-mail to [email protected]. A copy of the petition for 
leave to intervene and request for hearing should also be sent to the 
Office of the General Counsel, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001, and because of continuing disruptions in 
delivery of mail to United States Government offices, it is requested 
that copies be transmitted either by means of facsimile transmission to 
301-415-3725 or by e-mail to [email protected]. A copy of the 
request for hearing and petition for leave to intervene should also be 
sent to Mr. Edward J. Cullen, Deputy General Counsel, Exelon BSC--
Legal, 2301 Market Street, Philadelphia, PA 19101, attorney for the 
licensee.
    Nontimely filings of petitions for leave to intervene, amended 
petitions, supplemental petitions and/or requests for hearing will not 
be entertained absent a determination by the Commission, the presiding 
officer or the presiding Atomic Safety and Licensing Board that the 
petition and/or request should be granted based upon a balancing of the 
factors specified in 10 CFR 2.714(a)(1)(i)-(v) and 2.714(d).
    For further details with respect to this action, see the 
application for amendment dated October 1, 2002, which is available for 
public inspection at the Commission's PDR, located at One White Flint 
North, 11555 Rockville Pike (first floor), Rockville, Maryland. 
Publicly available records will be accessible from the Agencywide 
Documents Access and Management System's (ADAMS) Public Electronic 
Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who 
encounter problems in accessing the documents located in ADAMS, should 
contact the NRC PDR Reference staff by telephone at 1-800-397-4209, 
301-415-4737, or by e-mail to [email protected].

    Dated at Rockville, Maryland, this 2nd day of October, 2002.

    For the Nuclear Regulatory Commission.
Carl F. Lyon,
Project Manager, Section 2, Project Directorate III, Division of 
Licensing Project Management, Office of Nuclear Reactor Regulation.